If t1=Time at which water is first added to cement, t2=Time when needle fails to penetrate 5 mm to 7 mm from bottom of the mould, t3=Time when the needle makes an impression but the attachment fails to do so, then what is initial setting time?

A. t2-t1
B. t2+t1
C. t3-t1
D. 2*t1
Answer» B. t2+t1