If ‘D’ is the duration ‘ES’ and ‘EF’ are then earliest start and finish times, ‘LS’ and ‘LF’ are latest start and latest finish times, the following relationship holds good. |
| A. | F = LF - EF |
| B. | IS = LF + D |
| C. | LF = LS - ES |
| D. | EF = ES + D |
| Answer» E. | |