MCQOPTIONS
Saved Bookmarks
1. |
If actual price of material is less than budgeted price then the |
A. | price variance is favorable |
B. | price variance is unfavorable |
C. | cost variance is favorable |
D. | cost variance is unfavorable |
Answer» B. price variance is unfavorable | |