1. |
If actual price of material is $700 and the budgeted price is $900 then the |
A. | cost variance is favorable |
B. | cost variance is unfavorable |
C. | price variance is favorable |
D. | price variance is unfavorable |
Answer» D. price variance is unfavorable | |