MCQOPTIONS
Saved Bookmarks
1. |
If 64 people were working for Project A, then01 how many days did it take to complete the work? |
A. | 44 days |
B. | 22 days |
C. | 33 days |
D. | 36 days |
E. | None of these |
Answer» D. 36 days | |