| 1. |
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be : |
| A. | 5 days |
| B. | 4 days |
| C. | 6 days |
| D. | 7 days |
| Answer» C. 6 days | |