If 30 men working 7 hours a day can do a piece of work in 18 days, in how many days will 21 men working 8 hours a day do the same work ?

A. 20 1/2 days
B. 22 1/2 days
C. 24 1/2 days
D. 25 days
Answer» C. 24 1/2 days