1.

How many workers are required for completing the construction work in 10 days? I. 20% of the work can be completed by 8 workers in 8 days II. 20 workers can complete the work in 16 days III. One-eighth of the work can be completed by 8 workers in 5 days

A. I and II only
B. II and III only
C. I only
D. III only
E. Any one of three
Answer» F.