How is plan driven development different from agile development ? |
| A. | Outputs are decided through a process of negotiation during the software development process |
| B. | Specification, design, implementation and testing are interleaved |
| C. | Iteration occurs within activities |
| D. | All of the mentioned |
| Answer» D. All of the mentioned | |