For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is |
| A. | dry rolling, wet rolling, application of screening and application of filler |
| B. | dry rolling, application of filler, wet rolling and application of screening |
| C. | dry rolling, application of screening, wet rolling and application of filler |
| D. | dry rolling, application of screening, application of filler and wet rolling |
| Answer» D. dry rolling, application of screening, application of filler and wet rolling | |