MCQOPTIONS
Saved Bookmarks
| 1. |
For normal M20 reinforced concrete, the time of removing the vertical form work for columns as per IS 456 is |
| A. | 1 day |
| B. | 3 days |
| C. | 14 days |
| D. | 28 days |
| Answer» B. 3 days | |