MCQOPTIONS
Saved Bookmarks
1. |
For a work order, standard time and time taken are 20 hours and 15 hours respectively. Time rate being Rs. 2 per hour, total wages payable under Rowan Premium Plan will be . |
A. | 40 |
B. | 37.50 |
C. | 35 |
D. | none of these |
Answer» C. 35 | |