For a manual operation observed time data are given below: Recorded time : 15 minute Rating of the worker : 80% Personal allowance : 0.6 minute Basic fatigue allowance : 0.8 minute Contingency work allowance : 12 minute Unavoidable delay allowance : 11 minute What is the standard time for the operation? |
| A. | 16.4 minute |
| B. | 175 minute |
| C. | 185 minute |
| D. | none of the above |
| Answer» E. | |