For a foundation, find the elapsed time in which 90% of ultimate settlement will occur. The coefficient of consolidation is 4*10-4cm2/s. The average drainage path is 50cm.

A. 56.38 days
B. 43.78 days
C. 61.34 days
D. 78.23 days
Answer» D. 78.23 days