For 2.5 cm c.c. floor for 100 sq m of area and 10% for contingency what amount of cement concrete will be required? |
A. | 5.75 cu m |
B. | 2.75 cu m |
C. | 2.5 cu m |
D. | 5.0 cu m |
Answer» C. 2.5 cu m | |