Followings are major tasks of Test planning activity. Arrange them in correct order.1. Determine Test approach2. Determine Required test resources3. Determine scope and risks and identify objectives of testing4. Implement the test policy and/or the test strategy5. Determine the exit criteria6. Schedule test analysis and design tasks, test implementation, execution and evaluation |
| A. | 3,1,2,5,4,6 |
| B. | 3,1,2,5,6,4 |
| C. | 3,2,1,5,4,6 |
| D. | 3,1,4,2,6,5 |