Estimated time T, and variance of the activities 'V on the critical path in a PERT new work are given in the following table: Activity \[{{\mathbf{T}}_{\mathbf{e}}}\] (days) V \[{{\left( \mathbf{days} \right)}^{\mathbf{2}}}\] a 17 4 b 15 4 c 8 1 The probability of completing the project in 43 days is:

A. 15.6%              
B. 0.5
C. 81.4%              
D. 0.9
Answer» D. 0.9