Estimated time T, and variance of the activities 'V on the critical path in a PERT new work are given in the following table: Activity \[{{\mathbf{T}}_{\mathbf{e}}}\] (days) V \[{{\left( \mathbf{days} \right)}^{\mathbf{2}}}\] a 17 4 b 15 4 c 8 1 The probability of completing the project in 43 days is: |
| A. | 15.6% |
| B. | 0.5 |
| C. | 81.4% |
| D. | 0.9 |
| Answer» D. 0.9 | |