                                    Efficiency Ratio= | 
                            
| A. | Number of actual working days in a period x 100 Number of working days in the budget period | 
| B. | Actual hours worked x 100 Budgeted hours | 
| C. | Standard hours for actual production x 100 Actual hours worked | 
| D. | Standard hours for actual productionx 100 Budgeted standard hours | 
| Answer» D. Standard hours for actual productionx 100 Budgeted standard hours | |