Cut and fill of earthwork is performed while constructing a new rail line on undulating surface. Which of the following condition should be maintained so that construction cost is minimized? |
| A. | Quantity of cut = Quantity of fill |
| B. | Construction cost is independent of quantity of cut and fill |
| C. | Quantity of cut > Quantity of fill |
| D. | Quantity of cut < Quantity of fill |
| Answer» B. Construction cost is independent of quantity of cut and fill | |