Consider the following steps involved in hamrner forging a connecting rod from bar Stock 1. Blocking 2. Trimming 3. Finishing 4. Fullering 5. Edging Which of the following is the correct sequence of operations? |
| A. | 1, 4, 3, 2 and 5 |
| B. | 4, 5, 1, 3 and 2 |
| C. | 5, 4, 3, 2 and 1 |
| D. | 5, 1, 4, 2 and 3 |
| Answer» C. 5, 4, 3, 2 and 1 | |