Consider a case, in which the actual production rate of the well is lower than that predicted based on the IPR equation, and also the bottom hole pressure measurement shows it to be lower than the expected value then what is the cause of this situation? |
A. | By a restriction in the wellbore |
B. | By formation damage |
C. | By an increase in reservoir pressure |
D. | No formation damage |
Answer» C. By an increase in reservoir pressure | |