Below are given some general steps for undertaking cost benefit analysis:(a) Describing quantitatively the inputs and outputs of the programme/project(b) Estimating the social and benefits of the inputs and outputs of the programme/projects(c) Comparing the benefits and costs(d) Specifying the programme/project clearlyWhat will be the appropriate sequence in this regard? Choose your answer from the options given below:

A. (a), (b), (c) and (d)
B. (d), (a), (b) and (c)
C. (c), (d), (a) and (b)
D. (b), (c), (d) and (a)
Answer» C. (c), (d), (a) and (b)