As a test manager you will be getting delayed delivery of build for testing which has to be deployed on time. You have limited resources. By applying which measures are you able to perform testing in given time?

A. Argue with development team and convince them to deliver build on time.
B. Ask for more resources.
C. Request customer about extending time.
D. Prioritize testing based on risk & make sure critical functionality is tested earlier.
Answer» E.