Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work for alternate days and Amit starts the work first, then in how many days 35/36 parts of whole work will be completed?

A. 10 days
B. 12 days
C. 5 days
D. 8 days
Answer» B. 12 days