Arrange the following to obtain the correct procedure of soil density by sand replacement method.I. Cylinder is placed over a trayII. Tray with central hoe is placed in groundIII. Test hole is dugIV. The cylinder valve is opened |
| A. | (I), (II), (III), (IV) |
| B. | (II), (III), (I), (IV) |
| C. | (I), (III), (II), (IV) |
| D. | (II), (III), (IV), (I) |
| Answer» C. (I), (III), (II), (IV) | |