Anubhav can complete a job in 8 days working 7 hours a day and Vishal can complete the same work in 7 days working 6 hours a day. If both of them start on the same job together working 8 hours a days, then how many days are required to finish the job? |
| A. | 2 days |
| B. | 3 days |
| C. | 4 days |
| D. | 5 days |
| E. | None of these |
| Answer» C. 4 days | |