Anubhav can complete a job in 8 days working 7 hours a day and Vishal can complete the same work in 7 days working 6 hours a day. If both of them start on the same job together working 8 hours a days, then how many days are required to finish the job?

A. 2 days
B. 3 days
C. 4 days
D. 5 days
E. None of these
Answer» C. 4 days