An activity in a project management network is |
A. | The beginning or end of a specified job |
B. | An element of work entailed in the project |
C. | Represented by a circle in a network with a number in it |
D. | The progress of work up to a certain limit |
Answer» C. Represented by a circle in a network with a number in it | |