According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as |
| A. | the most likely time estimate |
| B. | optimistic time estimate |
| C. | pessimistic time estimate |
| D. | expected time estimate |
| Answer» D. expected time estimate | |