A small project consists of 3 activates P, Q and R to be executed in that sequence. The relationship between Time Duration (in ‘Units’ of time – T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith:P Q R TCTCTC825063408400923573201037510225829512350112159275 For a total duration of 25 units of time, the least total direct cost for the complete project will be |
| A. | 965 units |
| B. | 950 units |
| C. | 940 units |
| D. | 925 units |
| Answer» E. | |