1.

A project with the production cost of Rs. 100 crores, has 20,000 man-months as direct labour, of which 60% is non-productive time. The labour cost as estimated while tendering is 20 % of the project cost. If 15 % of the wastage resulting from non-productive time is eliminated by using improved methods, the resulting saving in labour cost will be

A. 14.5%
B. 18.5%
C. 22.5%
D. 26.5%
Answer» D. 26.5%


Discussion

No Comment Found