A project with the production cost of Rs. 100 crores, has 20,000 man-months as direct labour, of which 60% is non-productive time. The labour cost as estimated while tendering is 20 % of the project cost. If 15 % of the wastage resulting from non-productive time is eliminated by using improved methods, the resulting saving in labour cost will be |
A. | 14.5% |
B. | 18.5% |
C. | 22.5% |
D. | 26.5% |
Answer» D. 26.5% | |