A project manager estimated that he would complete the project in time if he hires 42 people for 38 days. At the end of 30 days he realized that only 3/5th of the work is complete. How many more men does he need to hire to complete the work in time? |
| A. | 71 |
| B. | 47 |
| C. | 63 |
| D. | 60 |
| Answer» D. 60 | |