A PERT network has three activities on critical path with mean time 3, 8 and 6, and standard deviation 1, 2 and 3 respectively. The probability that the project will be completed in 20 days is:

A. 0.5
B. 0.79
C. 0.84
D. 0.95
Answer» C. 0.84