1.

A newly constructed water treatment facility cost $2 million. It is estimated that the facility will need renovating every 30 years at a cost of $1 million. Annual repairs and maintenance are estimated to be$100,000 per year. At an interest rate of 6%, determine the capitalizedcost of the facility.

A. 3579806
B. 3877482
C. 4301205
D. 3360343
Answer» C. 4301205