A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is : |
| A. | 75 |
| B. | 100 |
| C. | 125 |
| D. | 50 |
| Answer» C. 125 | |