

MCQOPTIONS
Saved Bookmarks
1. |
A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job ? |
A. | 4 |
B. | 6 |
C. | 8 |
D. | 7/2 |
Answer» C. 8 | |