MCQOPTIONS
Saved Bookmarks
| 1. |
A major difference between the procedure of construction in bored piles and cast-in-situ driving piles is ___________ |
| A. | Driving equipment |
| B. | Method of driving |
| C. | Concrete filling |
| D. | None of the mentioned |
| Answer» B. Method of driving | |