A grader working at 75% efficiency is used in clearing ditches and levelling and reshaping roads. It requires 3 passes while running at a speed of 5 kmph. If the lane length is 1 km, the total time (in h) required to complete grading one lane will be

A. 1.00
B. 0.75
C. 0.80
D. 0.25
E. 0.50
Answer» F.