A does 2/5 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in |
| A. | <table><tr><td rowspan="2">6</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>12</center></td><td rowspan="2">days </td></tr><td align="center">13</td></table> |
| B. | <table><tr><td rowspan="2">8</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>2</center></td><td rowspan="2">days </td></tr><td align="center">11</td></table> |
| C. | 10 days |
| D. | 18 days |
| Answer» E. | |