| 1. |
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8 th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is : |
| A. | 18 |
| B. | 10 |
| C. | 12 |
| D. | 16 |
| Answer» E. | |