MCQOPTIONS
Saved Bookmarks
| 1. |
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now so that the work may finish in time ? |
| A. | 48 |
| B. | 56 |
| C. | 40 |
| D. | 50 |
| Answer» C. 40 | |