A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that 3/4 of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?

A. 40
B. 20
C. 30
D. 15
Answer» C. 30