1.

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one- third of the road in made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A. 100
B. 60
C. 50
D. 75
Answer» E.