A contractor hire Amitabh Arora to complete the work and Amitabh can do the work in 25 days. Amitabh worked for 5 days and after that Bindu singh completed it in 20 days. In how many days will Amitabh and Bindu together finish the work?

A. 25 days 2
B. 25 days
C. 15 days
D. 23 days 2
E. None of these
Answer» B. 25 days