| 1. |
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 2/5 th of the work is finished. How many additional men be employed so that the work may be completed on time, each man now working 9 hours a day? |
| A. | 35 |
| B. | 40 |
| C. | 45 |
| D. | None of these |
| Answer» B. 40 | |