| 1. |
A computer lab having a load of 450 MJ/day is cooled round the clock. It requires an air – conditioning plant of capacity about: |
| A. | 2.75 ton |
| B. | 1.5 ton |
| C. | 2 ton |
| D. | 1.75 ton |
| Answer» C. 2 ton | |