A completes a piece of work in 4 days and B completes it in 6 days. If they both work on it together, then the number of days required to complete the same work is |
| A. | 3 5 days 2 |
| B. | 2 3 days 5 |
| C. | 2 2 days 5 |
| D. | 3 2 days 5 |
| Answer» D. 3 2 days 5 | |