A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work? |
| A. | 37 ½ days |
| B. | 22 days |
| C. | 31 days |
| D. | 22 days |
| Answer» B. 22 days | |