A city has a projected population of 60,000 spread over area of 50 hectare. Find the design discharge for the separate sewer line by assuming rate of water supply of 250 LPCD and out of this total supply only 75 % reaches in sewer as wastewater. Make necessary assumption whenever necessary. |
A. | 0.26 m<sup>3</sup>/s |
B. | 0.6 m<sup>3</sup>/s |
C. | 0.76 m<sup>3</sup>/s |
D. | 3.26 m<sup>3</sup>/s |
Answer» B. 0.6 m<sup>3</sup>/s | |