1.

A certain part is produced in a batch size of 50 units and requires a sequence of 8 operations in the plant. The average set-up time and average non-operation time per operation are3 hours and 7 hours, respectively. The average operative time per machine per part is 6 minutes. What is the manufacturing lead time?

A. 100 hours                     
B. 120 hours
C. 150 hours                     
D. 180 hours
Answer» C. 150 hours                     