A certain part is produced in a batch size of 50 units and requires a sequence of 8 operations in the plant. The average set-up time and average non-operation time per operation are3 hours and 7 hours, respectively. The average operative time per machine per part is 6 minutes. What is the manufacturing lead time? |
| A. | 100 hours |
| B. | 120 hours |
| C. | 150 hours |
| D. | 180 hours |
| Answer» C. 150 hours | |