1.

A certain number of men can complete a work in 17 days working 8 hour a day. If the number of people is decreased to 60%. Then, find in how many hrs in a day should the remaining people work to complete the work in 51/2 days?

A. 20
B. 9
C. 12
D. 12
Answer» B. 9